1
|
Bhiwadi (Rajasthan)
|
Civil Work Completed.
Centre dedicated to the Nation on 31st August 2020.
AICTE approval received
Machine and Labs Planned – 102
Machine and Labs received – 59
Number of units assisted: 1,121 nos.
Number of trainees trained: 15,742 nos.
|
|
2
|
Durg (Chhattisgarh)
|
Balance civil work complete by March 2026
Overall Completion – 90%
Training Started
AICTE approval received
Machine and Labs Planned – 86
Machine and Labs received – 57
Number of units assisted: 430 nos.
Number of trainees trained: 15,422 nos.
|
|
3
|
Bengaluru (Karnataka)
|
Balance civil work complete
Training Started
Machine and Labs Planned – 138
Machine and Labs received – 1
Number of units assisted: 59 nos.
Number of trainees trained: 20,513 nos.
|
|
4
|
Rohtak (Haryana)
|
Civil Work Completed.
Centre dedicated to the Nation on 17th September 2021
Training Started
AICTE approval received
Machine and Labs Planned – 83
Machine and Labs received - 56
Number of units assisted: 645 nos.
Number of trainees trained: 12,620 nos.
|
|
5
|
Pudi (Andhra Pradesh)
|
Civil Work Completed.
Centre dedicated to the Nation on 10th March 2021
Training Started
AICTE approval received
Machine and Labs Planned – 104
Machine and Labs received - 57
Number of units assisted: 207 nos.
Number of trainees trained: 13,235 nos. |
|
6
|
Baddi (Himachal Pradesh)
|
Civil Work Completed.
Centre dedicated to the Nation on 14th February 2024
Training started
AICTE approval received
Machine and Labs Planned – 78
Machine and Labs received - 58
Number of units assisted: 192 nos.
Number of trainees trained: 7,083 nos. |
|
7
|
Sitarganj (Uttarakhand)
|
Civil Work Completed
Training Started
Machine and Labs Planned – 81
Machine and Labs received – 60
Number of units assisted: 332 nos.
Number of trainees trained: 7,562 nos.
|
|
8
|
Puducherry
|
Civil Work Completed.
Centre dedicated to the Nation on 12th January 2022
Training Started
Machine and Labs Planned – 57
Machine and Labs received - 25
Number of units assisted: 339 nos.
Number of trainees trained: 15,311 nos.
|
|
9
|
Bhopal (Madhya Pradesh)
|
Civil Work Completed.
Centre dedicated to the Nation on 10th March 2021
Training Started
AICTE approval received
Machine and Labs Planned – 97
Machine and Labs received - 55
Number of units assisted: 729 nos.
Number of trainees trained: 15,037 nos.
|
|
10
|
Kanpur (Uttar Pradesh)
|
Civil Work Completed.
Centre dedicated to the Nation on 14th February 2024
Training Started
Machine and Labs Planned – 87
Machine and Labs received - 55
Number of units assisted: - 178 nos.
Number of trainees trained: 3,257 nos. |
|
11
|
Imphal (Manipur)
|
Civil Work Completed.
Centre dedicated to the Nation on 14th February 2024
Training Started
Machine and Labs Planned : 83
Machine and Labs received : 35
Machine Procurement under process
Number of units assisted: 310 nos.
Number of trainees trained: 4,348 nos.
|
|
12
|
Ernakulam (Kerala)
|
Overall Completion – 75%
Balance civil work complete by March 2026
Machine and Labs Planned – 81
Machine Procurement under process
|
|
13
|
Greater Noida (Uttar Pradesh)
|
Civil Work Completed.
Centre dedicated to the Nation on 14th February 2024
Training Started
Machine and Labs Planned : 92
Machine Procurement under process
Number of units assisted : 48 nos.
Number of trainees trained : 5,774 nos.
|
|
14
|
Patna (Bihar)
|
Civil Work Completed
Training Started
Machine and Labs Planned : 84
Machine and Labs received – 18
Number of units assisted: 561 nos.
Number of trainees trained : 561 nos.
|
|
15
|
Sriperumbudur (Tamil Nadu)
|
Overall Completion – 67%
Balance civil work complete by March 2026
Machine and Labs Planned – 91
Machine Procurement under process
|