100 Days Program

For the week ending: 15.10.2019



SL. No. Intervention / Idea Status
1 Creation of 2,00,000 new employment opportunities through utilization of Rs.1000 crore margin money subsidy in 100 days with establishment of 30,000 new micro enterprises under Prime Minister’s Employment Generation Programme (PMEGP) [@ 7.62 employment per enterprise] • 24,138 Projects financed
• 1, 93,104 Estimated Employment opportunities created.
2 Inauguration of 50 traditional artisan-based clusters under SFURTI • 51 Clusters have been completed
3 Inauguration of 10 and approval of 40 enterprise-driven-industrial clusters under MSE-Cluster Development Programme • 10 projects have been commissioned.
• 43 projects have been approved
4 Inauguration of 3 new Technology Centres under Technology Centers Systems Programme (TCSP) The construction of 3 Technology Centres at Bhiwadi, Bhopal & Pudi is in progress as detailed below.
SL. No. Technology Centre (Location) Readiness of the Technology Centre for operations
1 Bhiwadi, Rajasthan Ready for inauguration. Training already started
2 Bhopal, Madhya Pradesh The building is ready except permanent power. Machines have been installed. General lighting available through DG Set. Permanent Power is expected before 30th October 2019. This Centre is Operations Ready.
3 Pudi, Andhra Pradesh The building is ready except permanent power. Machines have been installed. General lighting available through DG Set. Permanent Power is expected before 30th October 2019. This Centre is Operations Ready.
4 Tinsukhia, Assam Ready for Inauguration
5 Launch of 10 Solar Charkha clusters under Mission Solar Charkha 11 Solar Charkha Clusters approved.
6 1,00,000 youth to be skilled through Technology Centers and other Training Institutions of the Ministry. 1,05,626 trainees have been imparted training by Technology Centres, National Small Industries Corporation (NSIC) and Khadi & Village Industries Commission (KVIC) of the Ministry.
(From 5th July 2019 to 20th September 2019)